Page 69 - Improving Machinery Reliability
P. 69

Requirements Specijication   41

                         For example, Figure 1-26 represents one of many steam-turbine latching and
                       startup instructions  that  was  developed for both purposes,  that  is, reference
                       information and field-posted instructions. The vendor should be contractually
                       obligated to prepare these and similar illustrated instructions.
                         Figure  1-27 belongs  in the surveillance data category. This tabulation pro-
                       vides  key  input for vibration  spectrum  analysis  techniques  that are an  indis-
                       pensable troubleshooting tool for modern process plants. Again, the data should
                       be provided  by  the equipment  vendor  before plant  startup. Efforts  to acquire
                       this  information  after the  equipment  vendor  has received  full payment  for
                       machinery and services are usually quite costly and frustrating.
                     2. Equipment specification sheets, such as API data sheets and supplementary data
                       used at time of purchase.
                     3. Cross-section drawings showing the equipment assembly. These drawings must
                       be dimensionally accurate. Dimensional outline drawings should also be included.
                     4. Bill of materials or complete parts list identifying components and materials of
                       construction.






                                          ET-IIB  STEAM TURBINE, LATCHING
                                            AND STARTUP INSTRUCTIONS