            5.6 Recovery boiler installation estimate
            5.6.1 Erect drum, generating bank, integral economizers multiple
            header type sheet 1

                                                     Installation man-hour
                                                  Historical     Estimate

                                               MH      Unit  Qty  Unit   BM
            Erect drum, generating bank, and integral                    0
              economizer
            Install steam drum
            Steam drum (200,001                3.80    Ton   0    Ton    0
              LB<¼weight<¼300,000 LB)
            Steam drum trim piping             260.00  Boiler  0  Boiler  0
            Drum internals—remove and reinstall  136.00  Boiler  0  Boiler  0
            Generating bank
            Generating tube sections and headers—unload  10.00  Ton  0  Ton  0
              and handle
            Set rigging for hoisting assemblies  60.00  Boiler  0  Boiler  0
            Hoist into place                   1.50    Ton   0    Ton    0
            Weld tubes to header stubs—2-1/2 diameter,  2.40  EA  0  EA  0
                                    00
              TIG no PWHT
            Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
            Integral economizers multiple header type
            Economizer tube sections and headers—unload  10.00  Ton  0  Ton  0
              and handle
            Set rigging for hoisting assemblies  60.00  Boiler  0  Boiler  0
            Hoist into place                   1.50    Ton   0    Ton    0
                                    00
            Weld tubes to header stubs—2-1/2 diameter,  2.40  EA  0  EA  0
              TIG no PWHT
            Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
            Baffles—place and weld including clips  60.00  Ton  0  Ton   0
            Vibration bars                     65.00   Ton   0    Ton    0
            Buckstays                          40.00   Ton   0    Ton    0
            Casing and hoppers                 55.00   Ton   0    Ton    0
            Doors                              55.00   Ton   0    Ton    0