Page 112 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 112

Pulp and paper Chapter  5 85


             5.6.2  Erect headers/panels, wall/roof tubes, weld tubes
             and panels sheet 2


                                                                 Installation
                                                                 man-hour

                                                  Historical      Estimate
                                                 MH    Unit   Qty  Unit  BM
             Erect headers/panels/wall/roof and weld tubes               0
               and panels
             Boiler sidewall tubes
             Wall panels—shop assembled with headers  10.00  Ton  0  Ton  0
             Fit and weld filler joining membrane panels  0.70  LF  0  LF  0
             Furnace front wall tubes
             Headers—loose                       15.00  Ton   0    Ton   0
             Wall panels—shop assembled without headers  10.00  Ton  0  Ton  0
                                    00
             Weld tubes to header stubs—2-1/2 diameter, TIG  2.40  EA  0  EA  0
               no PWHT
             Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
             Fit and weld filler joining membrane panels  0.70  LF  0  LF  0
             Furnace roof tubes
             Headers—loose                       30.00  Ton   0    Ton   0
             Tubes—loose, furnace including screen  30.00  Ton  0  Ton   0
             Weld tubes to header stubs—3 diameter, TIG no  3.00  EA  0  EA  0
                                  00
               PWHT
             Furnace sidewall tubes
             Headers—loose                       15.00  Ton   0    Ton   0
             Wall panels—shop assembled without headers  10.00  Ton  0  Ton  0
             Weld tubes to header stubs—2-1/2 diameter, TIG  2.40  EA  0  EA  0
                                    00
               no PWHT
             Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
             Fit and weld filler joining membrane panels  0.70  LF  0  LF  0
             Furnace rear wall tubes
             Furnace rear wall tubes (wall panel—membrane)  12.00  Ton  0  Ton  0
             Furnace rear wall tubes (loose)     30.00  Ton   0    Ton   0
             Weld tubes to header stubs—2-1/2 diameter, TIG  2.40  EA  0  EA  0
                                    00
               no PWHT
             Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
             Fit and weld filler joining membrane panels  0.70  LF  0  LF  0