Page 107 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 107

80   Industrial process plant construction estimating and man-hour analysis


            5.3 General scope of field work required for each recovery
            boiler sheet 1

            5.3.1 Scope of work-field erection
            Pressure parts

               Install steam drum
               Drums include straps and/or U-bolts: steam drum
               Steam drum trim piping
               Drum internals—remove and reinstall
               Generating bank
               Generating tube sections and headers—unload and handle
               Set rigging for hoisting assemblies
               Hoist into place
                                           00
               Weld tubes to header stubs—2-1/2 diameter, TIG weld
               Fit and weld filler bar at tube welds
               Integral economizers for recovery units—multiple header type
               Economizer tube sections and headers—unload and handle
               Set rigging for hoisting assemblies
               Hoist into place
                                           00
               Weld tubes to header stubs—2-1/2 diameter, TIG weld
               Fit and weld filler bar at tube welds
               Baffles—place and weld including clips
               Vibration bars
               Backstays
               Casing and hoppers
               Doors

               Headers, furnace, and waterwall panels
               Boiler sidewall tubes
               Wall panels—shop assembled with headers
               Fit and weld filler joining membrane panels

               Furnace front wall tubes
               Headers—loose
               Wall panels—shop assembled without headers
                                           00
               Weld tubes to header stubs—2-1/2 diameter, TIG weld
               Fit and weld filler bar at tube welds
               Fit and weld filler joining membrane panels

               Furnace roof tubes
               Headers—loose
               Tubes—loose, furnace including screen
               Weld tubes to header stubs—3 diameter, TIG weld
                                        00
               Furnace sidewall tubes
               Headers—loose
               Wall panels—shop assembled without headers
               Weld tubes to header stubs—2-1/2 diameter, TIG weld
                                           00
               Fit and weld filler bar at tube welds
               Fit and weld filler joining membrane panels