Page 104 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 104

Waste heat boiler Chapter  4 77


             4.7.2  Boiler casing sheet 2

             Description                                    MH           Unit
             Erect casing—generating bank, boiler, and penthouse  62     Ton




             4.8 Structural steel installation estimate

             4.8.1  Structural steel sheet 1

                                                Historical        Estimate
                                          MH     Qty     Unit  Qty  Unit  BM
             Erect boiler structural steel                               0
             Column line “1" (west)       24.00  51.1    Ton   0    Ton  0
             Column line “6” (east)       24.00  10.7    Ton   0    Ton  0
             Column line “7” (east)       24.00  10.7    Ton   0    Ton  0
             Column line “A” (north)      24.00  14.0    Ton   0    Ton  0
             Column line “B” (north)      24.00  37.9    Ton   0    Ton  0
             Column line “F” (south)      24.00  30.2    Ton   0    Ton  0
             Column line “G” (south)      24.00  37.2    Ton   0    Ton  0
             Erect penthouse steel        24.00  45.8    Ton   0    Ton  0
             Install platform, grating, and handrail @                   0
               El. 100 -0 to 184 -0 00
                           0
                     00
                   0
             Platform framing             0.15   15488.0  SF   0    SF   0
             Grating                      0.20   15488.0  SF   0    SF   0
             Handrail                     0.25   2816.0  LF    0    LF   0
             Install stair nos. 1 and 2                                  0
             Structural steel             24.00  14.4    Ton   0    Ton  0
             Platform framing             0.15   1440.0  SF    0    SF   0
             Grating                      0.20   1440.0  SF    0    SF   0
             Handrail                     0.25   320.0   LF    0    LF   0
             Stair treads                 0.85   192.0   EA    0    EA   0



             4.8.2  Boiler casing sheet 2


                                    Installation man-hour
                                                  Historical      Estimate
                                              MH   Qty   Unit  Qty  Unit  BM
             Erect casing—generating bank, boiler, and  62  19.0  Ton  0  Ton  0
               penthouse
   99   100   101   102   103   104   105   106   107   108   109