78 Industrial process plant construction estimating and man-hour analysis
4.9 Structural steel and boiler casing-equipment installation
man hours
Actual Estimated
Facility—biomass plant major equipment MH BM
Erect boiler structural steel 4601 0
Erect penthouse steel 1100 0
Install platform, grating, and handrail @ El. 100 -0 to 184 -0 00 6140 0
00
0
0
Install stair Nos. 1 and 2 1094 0
Erect casing—generating bank, boiler, and penthouse 1180 0
Structural steel and boiler casing-equipment installation man-hours 14116 0