78  Industrial process plant construction estimating and man-hour analysis


            4.9 Structural steel and boiler casing-equipment installation
            man hours


                                                             Actual  Estimated
            Facility—biomass plant major equipment           MH     BM
            Erect boiler structural steel                    4601   0
            Erect penthouse steel                            1100   0
            Install platform, grating, and handrail @ El. 100 -0 to 184 -0 00  6140  0
                                               00
                                                     0
                                             0
            Install stair Nos. 1 and 2                       1094   0
            Erect casing—generating bank, boiler, and penthouse  1180  0
            Structural steel and boiler casing-equipment installation man-hours  14116  0