Waste heat boiler Chapter  4 75


             4.4.3  Down comers and code piping sheet 3

                                                Historical        Estimate
             Description                   MH      Qty   Unit  Qty  Unit  BM

             Erect and install down comers and code                      0
               piping
                              00
             Handle down comers; 12 OD 0.562  1.32  280.0  LF  0    LF   0
               WT 40 0
             Down comers; 12 OD 0.562 WT BW  12.6  14.0  EA    0    EA   0
                         00
                    00
             Handle 12 300# BW main stop valve and  5.4  2.0  EA  0  EA  0
               Ck valve
             12  0.562 WT CS BW            12.60   4.0   EA    0    EA   0
               00
             Handle 10 300# BW feed water stop and  136.00  2.0  EA  0  EA  0
                    00
               Ck valve
             10  0.562 WT CS BW            4.00    4.0   EA    0    EA   0
               00
             Handle 8 300# BW spray control valves  7.20  4.0  EA  0  EA  0
                   00
             8  0.562 WT CS BW             8.40    8.0   EA    0    EA   0
              00
             Handle 3 300# safety valves   2.70    3.0   EA    0    EA   0
                   00
             3  0.375 WT CS BW             1.50    6.0   EA    0    EA   0
              00
             Handle 3 300# control valves—boiler  2.70  2.0  EA  0  EA   0
                   00
             3  0.375 WT CS BW             1.50    4.0   EA    0    EA   0
              00
             Handle 2 300# control valves—boiler  1.00  2.0  EA  0  EA   0
                   00
             2  0.375 WT CS BW             1.10    4.0   EA    0    EA   0
              00
             Handle 4 300# flanged flow elements  3.60  6.0  EA  0  EA   0
                   00
             4 300# Bolt up                1.60    12.0  EA    0    EA   0
              00
             Handle 10  0.562 pipe         1.10    160.0  LF   0    LF   0
                    00
             Handle 8  0.562 pipe          0.88    160.0  LF   0    LF   0
                   00
             Handle 4  0.375 pipe          0.28    225.0  LF   0    LF   0
                   00
                   00
             Handle 3  0.375 pipe          0.21    160.0  LF   0    LF   0
             Handle 2  0.375 pipe          0.18    160.0  LF   0    LF   0
                   00
             4.5 Waste heat boiler—Equipment installation man-hours
                                                             Actual  Estimated
             Facility—biomass plant major equipment          MH      BM
             Install steam and mud drums                     1103    0
             Generating bank tubes                           3628    0
             Ground assembly—headers, furnace, and water wall panels  2692  0
             Erect headers and wall panels, fit and weld water wall panels  4432  0
             Fit and weld water wall tubes; 2-31/32 OD 0.203 WT, BW (TIG)  6912  0
                                       00
                                                00
             Erect, fit and weld primary/secondary headers and superheater  1514  0
               elements
             Burner system                                   280     0
             Soot blowers                                    1280    0
             Erect and install down comers and code piping   1509    0
             Waste heat boiler—equipment and piping installation man-hours  23351  0