72  Industrial process plant construction estimating and man-hour analysis


            4.3.3 Down comers and code piping sheet 3

            Description                                 MH              Unit
            Erect and install down comers and code piping
            Handle down comer; 12 OD 0.562 WT           1.32            LF
                             00
                                       00
            12  0.562 WT CS BW                          12.6            EA
              00
            Handle 12 300# BW valve                     5.4             EA
                    00
            Handle 10 300# BW valve                     4.50            EA
                    00
            Handle 8 300# BW spray control valves       7.20            EA
                   00
            Handle 3 300# safety/control valves         2.70            EA
                   00
            Handle 2 300# control valves—boiler         1.00            EA
                   00
            10  0.562 WT CS BW                          10.5            EA
              00
            8  0.562 WT CS BW                           8.40            EA
             00
            3  0.375 WT CS BW                           1.50            EA
             00
            2  0.375 WT CS BW                           1.10            EA
             00
            4 300# Flanged air flow elements            3.60            EA
             00
                    00
            Handle 10  0.562 pipe                       1.10            LF
            Handle 8  0.562 pipe                        0.88            LF
                   00
            4 300# Bolt connection                      1.60            EA
             00
   94   95   96   97   98   99   100   101   102   103   104