68 Industrial process plant construction estimating and man-hour analysis
00
00
0
Install 8 -0 6 -0 enclosure and six (6) rack and pinions, slide gates,
0
including chain wheel actuators between the meters.
Solid fuel is fed to the boiler in six (6) feed points, all on the front wall.
Fuel chutes
Install metering bin discharge chutes, expansion joints to stoker windswept
spouts, support bins, and drag chains for all six (6) bins.