             3.4.6  Recycle compressor reciprocating sheet 6

                                                  Historical      Estimate
             Description                      MH    Qty  Unit  Qty  Unit  BM

             Recycle compressor reciprocating                            0
             Frame and Gear                   340   1    EA    0    EA   0
                 00
             34 -5 Cylinder                   180   1    EA    0    EA   0
               0
                 00
             22 -0 Cylinder                   120   1    EA    0    EA   0
               0
             First stage suction damper       60    1    EA    0    EA   0
             First stage discharge damper     60    1    EA    0    EA   0
             Extended bearing and postal      60    1    EA    0    EA   0
             Lube oil consul 2 ea.            60    2    EA    0    EA   0
             Moister separator 3 ea.          60    3    EA    0    EA   0
             Full main tech deck              240   1    Lot   0    Lot  0
             IC Pipe—Interstate piping spools between  800  1  Lot  0  Lot  0
               coolers
             Rotor and extension shaft        240   1    EA    0    EA   0
             Motor stator                     180   1    EA    0    EA   0
             Motor enclosure (soleplates and Nc)  200  1  Lot  0    Lot  0

             3.5 Stripper unit—Equipment installation man-hours


                                                     Actual          Estimated
             Facility-Oil Refinery                   MH              BM
             Stripper vertical tower                 1180            0
             Drums                                   1127            0
             Heaters, heat exchangers, and air coolers  1835         0
             Pump—centrifugal                        858             0
             Filter and reactor                      1265            0
             Recycle compressor reciprocating        2780            0
             Equipment installation man-hours        9045            0