Page 92 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 92

64  Industrial process plant construction estimating and man-hour analysis


            3.4.4 Pump—Centrifugal sheet 4

                                                Historical        Estimate
            Description                     MH    Qty   Unit  Qty  Unit  BM

            Pump—centrifugal                                             0
            Feed charge pump (centrifugal)  0.60  600.0  HP   0    HP    0
                  0
              6  4  4 7.5 ton
               0
                     0
            Wash water pump (centrifugal)   2.00  40.0  HP    0    HP    0
              6 4.5 3.5 1.5 ton
            Stripper overhead pump (centrifugal)  1.50  100.0  HP  0  HP  0
              8 3 3 1.8 ton
            Stripper bottoms pump (centrifugal)  1.25  200.0  HP  0  HP  0
              9 3.5 3.5 2 ton
            Stripper overhead water pump (centrifugal)  24.00  0.8  HP  0  HP  0
              6 3 3 0.75


            3.4.5 Filter and reactor sheet 5

                                              Historical         Estimate

            Description                   MH    Qty   Unit  Qty   Unit   BM
            Filter and reactor                                           0
            Fuel gas filter               24    1     EA    0     EA     0
            Diolefin reactor ID-ft 9 T/T-ft 16  5.5  65  Ton  0   Ton    0
            Hydrotreating reactor ID-ft 9 T/T-ft 80  3.2  276  Ton  0  Ton  0
   87   88   89   90   91   92   93   94   95   96   97