Page 119 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 119

92   Industrial process plant construction estimating and man-hour analysis


            5.11 Reheat recovery boiler estimate data
            5.11.1 Erect drum, generating bank, integral economizers multiple
            header type sheet 1

            Description                                      MH        Unit
            Drums include straps and/or U-bolts
            100,001–200,000lbs                               4.60      Ton
            200,001–300,000lbs                               3.80      Ton
            Steam drum trim piping                           260.00    LOT
            Drum internals—remove and reinstall              136.00    Boiler
            Generating bank
            Generating tube sections and headers—unload and handle  10.00  Ton
            Set rigging for hoisting assemblies              60.00     Boiler
            Hoist into place                                 1.50      Ton
            Weld tubes to header stubs—2-1/2 diameter, TIG No PWHT  2.60  EA
                                    00
            Fit and weld filler bar at tube welds            1.00      Space
            Integral economizers multiple header type
            Economizer tube sections and headers—unload and handle  10.00  Ton
            Set rigging for hoisting assemblies              60.00     Boiler
            Hoist into place                                 1.50      Ton
            Weld tubes to header stubs—2-1/2 diameter, TIG No PWHT  2.60  EA
                                    00
            Fit and weld filler bar at tube welds            1.00      Space
            Baffles—place and weld including clips           60.00     Ton
            Vibration bars                                   65.00     Ton
            Buckstays                                        40.00     Ton
            Casing and hoppers                               55.00     Ton
            Doors                                            55.00     Ton




            5.11.2 Erect headers and panels, furnace wall and roof tubes, weld
            tubes and panels sheet 2

            Description                                         MH     Unit
            Erect headers and wall panels, fit and weld waterwall panels
            Boiler sidewall, furnace front wall, roof, sidewall and rear wall tubes
            Wall panels—shop assembled with headers             10.00  Ton
            Fit and weld filler joining membrane panels         0.70   LF
            Headers—loose                                       15.00  Ton
            Wall panels—shop assembled without headers          10.00  Ton
            Weld tubes to header stubs—2-1/2 diameter, TIG No PWHT  2.60  EA
                                    00
            Headers—loose                                       30.00  Ton
            Tubes—loose, furnace including screen               30.00  Ton
            Weld tubes to header stubs—3 diameter, TIG No PWHT  4.00   EA
                                  00
            Furnace rear wall tubes (wall panel—membrane)       12.00  Ton
            Furnace rear wall tubes (loose)                     30.00  Ton
            Fit and weld filler bar at tube welds               1.00   Space
            Fit and weld filler joining membrane panels         0.70   LF
   114   115   116   117   118   119   120   121   122   123   124