Page 123 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 123

96   Industrial process plant construction estimating and man-hour analysis


            5.12.2 Erect headers, panels, furnace wall, roof tubes, weld tubes
            and panels sheet 2


                                                  Historical     Estimate
                                                MH     Unit  Qty  Unit   BM
            Erect headers, panels, furnace wall, roof tubes              0
            Boiler sidewall tubes
            Wall panels—shop assembled with headers  10.00  Ton  0  Ton  0
            Fit and weld filler joining membrane panels  0.70  LF  0  LF  0
            Furnace front wall tubes
            Headers—loose                       15.00  Ton   0    Ton    0
            Wall panels—shop assembled without headers  10.00  Ton  0  Ton  0
            Weld tubes to header stubs—2-1/2 diameter, TIG  2.60  EA  0  EA  0
                                    00
              no PWHT
            Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
            Fit and weld filler joining membrane panels  0.70  LF  0  LF  0
            Furnace roof tubes
            Headers—loose                       30.00  Ton   0    Ton    0
            Tubes—loose, furnace including screen  30.00  Ton  0  Ton    0
            Weld tubes to header stubs—3 diameter, TIG no  4.00  EA  0  EA  0
                                 00
              PWHT
            Furnace sidewall tubes
            Headers—loose                       15.00  Ton   0    Ton    0
            Wall panels—shop assembled without headers  10.00  Ton  0  Ton  0
            Weld tubes to header stubs—2-1/2 diameter, TIG  2.60  EA  0  EA  0
                                    00
              no PWHT
            Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
            Fit and weld filler joining membrane panels  0.70  LF  0  LF  0
            Furnace rear wall tubes
            Furnace rear wall tubes (wall panel—membrane)  12.00  Ton  0  Ton  0
            Furnace rear wall tubes (loose)     30.00  Ton   0    Ton    0
                                    00
            Weld tubes to header stubs—2-1/2 diameter, TIG  2.60  EA  0  EA  0
              no PWHT
            Fit and weld filler bar at tube welds  1.00  Space  0  Space  0
            Fit and weld filler joining membrane panels  0.70  LF  0  LF  0