Page 125 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 125
98 Industrial process plant construction estimating and man-hour analysis
5.12.4 Install smelt spout and hood and auxiliary boiler support steel
and equipment, sheet 4
Installation man-hour
Historical Estimate
MH Unit Qty Unit BM
Smelt spout and hood 55.00 Ton 0 Ton 0
Auxiliary boiler support steel and equipment 0
Floor and hopper support steel 28 Ton 0 Ton 0
Suspension steel 30 Ton 0 Ton 0
Buckstays 36 Ton 0 Ton 0
Casing 95 Ton 0 Ton 0
Burner wind box—primary, secondary, 75 Ton 0 Ton 0
and tertiary
Primary burners 72.00 EA 0 EA 0
Lighters 5.00 EA 0 EA 0
Hoppers 95 Ton 0 Ton 0
Doors and frames 140 Ton 0 Ton 0
Seals 190 Ton 0 Ton 0
Expanded metal lathe 0.08 SF 0 SF 0
Closure plates 95 Ton 0 Ton 0
Instrument connection 200 Boiler 0 Boiler 0