94   Industrial process plant construction estimating and man-hour analysis


            5.11.5 Install tubular air heater, flues and ducts

            Description                                           MH    Unit
            Tubular air heater
            Tube sheets                                           28.00  Ton
            Baffle sheets—turn and vibration                      60.00  Ton
            Supports—tube sheets                                  20.00  Ton
            Erect grid support steel                              28.00  Ton
            Supports—main                                         18.00  Ton
            Tubes—steel                                           9.00  Ton
            Expand 2 ends                                         0.65  EA
                   00
            Expand 2-1/2 ends                                     0.95  EA
                      00
            Casing, veneer including batten bars and channels     64.00  Ton
            Casing, main and hoppers including expansion joints and doors  60.00  Ton
            Dampers                                               40.00  Ton
            Flues and ducts
            Flues and ducts—supports, hoppers, doors, expansion joints, and dampers  40.00  Ton
            Coupling guards                                       14.00  Ton