Page 129 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 129

Industrial package boiler Chapter  6 103


             6.4 D-type package boiler installation estimate
             6.4.1  Boiler and piping, flues, stack, economizer, and structural
             steel sheet 1

                                                    Historical    Estimate
                                                   MH    Unit  Qty  Unit  BM

             Boiler and piping, flues, stack, economizer, and            0
               structural sheet 1
             Unload, place, and set package boiler on foundation  8.0  Ton  0  Ton  0
             Install boiler piping                 140.0  Unit  0   Unit  0
             Erect stack
             Stack—knocked down                    1.8   LF    0    LF   0
             Stack—shop assembled                  28.0  Ton   0    Ton  0
             Unload, place, and set economizer (shop assembled)  20.0  Ton  0  Ton  0
             Structural steel                      24.0  Ton   0    Ton  0
             Platform framing                      0.2   SF    0    SF   0
             Grating                               0.2   SF    0    SF   0
             Handrail                              0.3   LF    0    LF   0
             Stair treads                          0.9   EA    0    EA   0
             Feedwater regulators                  55.0  EA    0    EA   0




             6.4.2  D-type package boiler installation man-hours

                                                             Estimated  Actual
                                                             BM        BM

             Boiler and piping, flues, stack, economizer, and structural sheet 1  0  0
             D-type package boiler installation man-hours    0         0
   124   125   126   127   128   129   130   131   132   133   134