Page 187 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 187

Coal-fired power plant Chapter  8 163


             8.24 FD, ID, primary air fan & pulverizer seal air fan estimate data
             8.24.1 Install FD, ID, primary air fan & pulverizer seal air fan sheet 1


                       Description                      MH     Unit
                       Install sole and base plates     2.00   EA
                       Attach fan to foundation—bolted connection  0.42  EA
                       Set fan housing split            4.00   EA
                       Set impeller assembly/shaft      4.00   EA
                       Alignment fan bearings           10.00  EA
                       Seal weld housing inside/outside  12.00  Job
                       Weld inlet cones and stud rings  4.00   Job
                       Weld shaft seal stud rings       4.00   Job
                       Coupling alignment               6.00   Job
                       Install damper                   10.00  EA