Page 189 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 189

Coal-fired power plant Chapter  8 165


             8.26 FD, ID, primary air fan & pulverized seal air fan installation
             man hours


                                                             Estimated  Actual
                                                             BM        BM
             Fans                                            0         0
             FD fan                                          0         0
             ID fan                                          0         0
             Primary air fan                                 0         0
             Pulverizer seal air fan                         0         0
             FD, ID, primary air fan, and pulverized seal air fan installation  0  0
               man-hours




             8.27 General scope of field work required for each bottom ash
             handling system

             Equipment consists of refractory-lined bottom ash chute and one (1) submerged
             ash drag chain conveyor.

                Bottom ash chute
                Submerged ash drag conveyor with outlet chute
                Shipped in sections:
                Head section—motor and drive shipped attached to head
                Neck section
                Transition section
                Straight section
                Tail section—take up shipped assembled
                Scope of work:
                Assembly of housing
                Assembly of drag chain
                Installation of drive units
                Pneumatic/hydraulic take-up units, including air piping
                Discharge chutes
                Grouting
                Refractory-lined chute on inlet of submerged ash drag
                All water piping to and from submerged ash drag and drains