Page 194 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 194

170   Industrial process plant construction estimating and man-hour analysis


            8.35 General scope of field work required for each electrostatic
            precipitator


               Casing
               Prefabricate wall and partition panels
               Install anvil beams and antisneak age baffles on end frames/roof beams and
               bottom baffles
               Set partition and wall panels; stabilize with top-end frames, bottom-end
               frames and intermittently with intermediate roof beams and supporting bot-
               tom baffles
               Install remaining intermediate roof beams and supporting bottom baffles
               Square and plumb casing and began weld out
               Complete casing welding, including the hoppers
               Drop in preassembled hoppers with lower alignment frames and scaffolding
               inside
               Secure interior cross ties between roof beams, end frames, and bottom
               baffles
               Hang inlet and outlet perforated plates
               Preassemble and mount inlet and outlet plenums
               Install inlet and outlet plenum cone sections
               Install platforms, stairways, and ladders

               Internals
               Lift and set collecting plates into ESP
               Join plate halves and attach plates to anvil beams
               Do preliminary alignment of collecting plates
               Preassemble discharge electrodes to high voltage frames
               Lift high voltage frames and rest on collecting plates

               Penthouse
               Preassemble hot roof sections
               Install hot roof sections
               Install lower alignment frames to discharge electrodes
               Suspend high voltage frames from support insulators
               Complete welding of penthouse walls and hot roof
               Weld out rapper sleeves (installed below)
               ESP roof
               Preassemble cold roof sections
               Insulate underside of cold roof
               Set cold roof sections and expansion joints
               Install roof handrail
               Install and weld out rapper sleeves
               Weld out cold roof
               Install rapper shafts, rapper adjusting studs, and rappers
               Align rappers
               Set TR sets
   189   190   191   192   193   194   195   196   197   198   199