Page 199 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 199

Coal-fired power plant Chapter  8 175


             8.36.6 Seal air system, dampers, stack, inlet/outlet plenum sheet 6

             Description                                 MH              Unit
             Erect seal air system
              Install seal air blower and heater system  260.00          Ea.
             Install dampers and access doors
              Install dampers                            50.00           Ea.
              Install 30   30 access doors               4.09            Ea.
                         00
                     00
             Erect stack
              Set bottom and upper section               60.00           Ea.
              Bolt bottom section to foundation          1.53            Ea.
              Fit and weld upper sections                0.75            LF
              Platform—360 deg                           0.10            SF
              Grating                                    0.15            SF
              Handrail                                   0.25            elf
              Step platforms                             6.00            Ea.
              Caged ladder                               0.35            LF
             Preassemble and erect inlet/outlet plenum
              Place and fit inlet and outlet plenum sections  11.40      Ton
              Weld inlet and outlet plenum sections      0.75            LF
             Erect inlet/outlet plenum
              Place and fit inlet plenum sections        22.00           Ton
              Place and fit outlet plenum sections       40.00           Ton
              Weld inlet and outlet plenum sections      0.75            LF




             8.36.7 Penthouse structural steel sheet 7

                       Description              MH             Unit

                       Penthouse structural steel and platforms
                        Erect structural steel  8.00           pcs
                        Bolted connections      1.00           Ea.
                        Platforms and stairs    160.00         lot
   194   195   196   197   198   199   200   201   202   203   204