Coal-fired power plant Chapter  8 179


             8.37.4 Frames/baffles, collecting plates, hopper auxiliaries,
             electrodes, hot roof sheet 4


                                              Historical        Estimate
             Description                   MH     Unit     Qty  Unit     BM
             Install bottom-end frames and bottom                        0
               support baffles
              Place and fit bottom-end frames  2.50  Ton   0    Ton      0
              Place and fit baffles        2.50   Ton      0    Ton      0
              Field bolts                  0.20   Ea.      0    Ea.      0
              Seal weld around bolts       0.35   LF       0    LF       0
              Field weld 1/4 fillet        0.35   LF       0    LF       0
                        00
              Full penetration field weld 1/2 double  16.00  Ea.  0  Ea.  0
                                   00
                bevel
             Install collecting plates                                   0
              Install collecting plates    3.50   Ea.      0    Ea.      0
              Bolt plates                  1.00   Ea.      0    Ea.      0
              Weld corner                  240.00  Job     0    Job      0
              Decking                      160.00  Job     0    Job      0
                                                                         0
              Install pneumatic hopper slide gates  7.80  Assembly  0  Assembly  0
               (12   12 )
                  00
                      00
              Install manual hopper slide gates  7.80  Assembly  0  Assembly  0
               (12   12 )
                  00
                      00
              Install TR controllers       6.00   Assembly  0   Assembly  0
             Install upper frames/electrodes                             0
              Install high voltage frames  16.00  Ea.      0    Ea.      0
              Load, haul, offload discharge  0.50  Ea.     0    Ea.      0
              electrodes
              Install spiked discharge electrodes 2 00  1.20  Ea.  0  Ea.  0
               diameter   40 0
             Preliminary alignment         480.00  Job     0    Job      0
             Install/weld hot roof                                       0
              Place and fit casing roof sections  27.50  Ton  0  Ton     0
              Weld roof casing             0.35   LF       0    LF       0
              Weld roof casing at corners  0.35   LF       0    LF       0