178   Industrial process plant construction estimating and man-hour analysis


            8.37.3 Penthouse, casing, hoppers, weld casing, frames/beams
            sheet 3


                                                     Historical     Estimate
            Description                          MH     Unit  Qty  Unit  BM
            Preassemble penthouse                                        0
              Place and fit penthouse roof sections  2.50  Ton  0  Ton   0
              Weld penthouse roof sections       2.15   LF    0    LF    0
              Place and fit penthouse sides and ends  2.50  Ton  0  Ton  0
              Weld penthouse sides and ends      2.15   LF    0    LF    0
            Erect casing                                                 0
              Rig and place side frame casing (row 1 and 3)  40.00  Ea.  0  Ea.  0
              Rig and place partition frame casing (row 2)  40.00  Ea.  0  Ea.  0
              Attach temporary guy lines to casing/turn buckles  6.67  Ea.  0  Ea.  0
            Set hoppers                                                  0
              Rig and place hoppers on support steel  1.50  Ton  0  Ton  0
              Field bolt list                    0.15   EA    0    EA    0
            Plumb, square, weld casing                                   0
              Plumb, square, and fit casing (turnbuckle)  360.00  Job  0  Job  0
              Weld side frame sections—3/8 square butt weld  0.75  LF  0  LF  0
                                  00
              Weld partition frame sections—3/8 square butt  0.75  LF  0  LF  0
                                      00
               weld
              Weld side wall casing corners      0.35   LF    0    LF    0
              Weld outside side wall casing 2–10  0.35  LF    0    LF    0
              Bevel beams 1/2 thick   12 00      2.50   Ea.   0    Ea.   0
                         00
              Place and fit beams                10.00  Ea.   0    Ea.   0
              Full penetration field weld 1/2 double bevel  16.00  Ea.  0  Ea.  0
                                   00
              Field bolts                        300.00  Lot  0    Lot   0
            Install top-end frames and intermediate roof                 0
              beams
              Place and fit top-end frames       40.00  Ton   0    Ton   0
              Place and fit roof beams           40.00  Ton   0    Ton   0
              Field bolts                        0.20   Ea.   0    Ea.   0
              Seal weld around bolts             0.35   Ea.   0    Ea.   0
              Field weld 1/4 fillet              0.35   LF    0    LF    0
                        00
              Full penetration field weld 1/2 double bevel  16.00  Ea.  0  Ea.  0
                                   00
   197   198   199   200   201   202   203   204   205   206   207