Coal-fired power plant Chapter  8 183


             8.39 Scope of field work required for structural steel and boiler
             casing


                Structural Steel
                Erect Boiler Structural Steel (Stairs, Platforms, Grating, and
                Handrails)
                Main steel
                Platform framing
                Grating
                Handrail
                Erect Penthouse Steel
                Install Platform, Grating, and Handrail
                Platform framing
                Grating
                Handrail

                Install Stair Nos. 1 and 2
                Structural steel
                Platform framing
                Grating
                Handrail
                Stair treads

                Erect Casing—Generating Bank, Boiler, and Penthouse