Page 209 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 209

Coal-fired power plant Chapter  8 185


             8.41 Structural steel and boiler casing installation estimate
             8.41.1 Erect structural steel and boiler casing sheet 1


                                                       Installation man-hour
                                                    Historical    Estimate
                                                   MH     Unit  Qty  BM  BM
             Flues and ducts                                             0
             Flues and ducts                       40.00  Ton       Ton  0
             Coupling guards                       14.00  Ton       Ton  0
             Structural steel
             Erect boiler structural steel                               0
             Main steel                            24.00  Ton       Ton  0
             Platform framing                      0.15  SF         SF   0
             Grating                               0.20   SF        SF   0
             Handrail                              0.25   LF        LF   0
             Erect penthouse steel, platform, grading, and               0
               handrail
             Main steel                            24.00  Ton       Ton  0
             Platform framing                      0.15   SF        SF   0
             Grating                               0.20   SF        SF   0
             Handrail                              0.25   LF        LF   0
             Install stair nos. 1 and 2                                  0
             Structural steel                      24.00  Ton       Ton  0
             Platform framing                      0.15   SF        SF   0
             Grating                               0.20   SF        SF   0
             Handrail                              0.25   LF        LF   0
             Stair treads                          0.85   EA        EA   0
             Erect casing—generating bank, boiler, and  62.00  Ton  Ton  0
               penthouse




             8.42 Structural steel and boiler installation man-hours estimated
             actual


                                                             BM          BM
             Flues and ducts                                 0           0
             Erect boiler structural steel                   0           0
             Erect penthouse steel, platform, grading, and Handrail  0   0
             Install stair nos. 1 and 2                      0           0
             Erect casing—generating bank, boiler, and penthouse  0      0
             Structural steel and boiler casing installation man-hours  0  0