Page 212 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 212

188 Industrial Process Plant Construction Estimating and Man-Hour Analysis


            9.2 General scope of field work required for each receiver

               Scope of Work-Field Erection
               Assemble L1, L2, and L3 core columns with crossbeams and cross braces
               Lift and install deck crossbeams between columns
               Lift L3 primary sun assembly with columns
               Lift and install all secondary steel and install grating, handrails, and ladders
               Lift and install all roof deck secondary steel and install grating, handrails,
               and ladders
               Lift and seal weld crane base plate and roof deck diamond plates
               Install crossbeams
               Bolted connections—crossbeams
               Lift ECV, load, haul, and set ECV
               Connect vertical struts to ECV ring girder
               Weld bumper plates to bumper stubs
               EVC in final position
               Set receiver sections on top of 600 ft tower
               Connect L1, L2, and L3 core columns at splice


            9.3 Receiver estimate data
            9.3.1 Assemble and erect core columns and cross-braces sheet 1

            Description                               MH                Unit

            Assemble columns; W10   77   39 0         6.5               Ton
            Install crossbeams; W10   49   10 0       6.5               Ton
            Install crossbeams; W16   40   10 0       6.5               Ton
            Install crossbeams; W10   50   10 0       6.5               Ton
            Install cross braces HSS8x8x.500          1.5               EA
            Bolted connections—cross braces           1.5               EA
            Lift and set                              20                EA
            Make up anchor bolts 8 ea.                0.5               EA



            9.3.2 Install secondary steel, platforms and ladders sheet 2


            Description                          MH                     Unit
            W6x12                                1.50                   Ton
            Bolted connections                   1.00                   EA
            Install grating                      0.20                   SF
            Install handrail                     0.27                   LF
            Install caged ladder                 0.35                   LF
            MC7x19.1                             1.50                   Ton
            Bolted connections                   1.00                   EA
            Weld mounting hardware               100.0                  EA