Page 216 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 216
192 Industrial Process Plant Construction Estimating and Man-Hour Analysis
9.5 Receiver installation man hours
Estimated Actual
IW IW
Erect core columns L1 1775 0
Erect core columns L2 (2 EA) 4035 0
Erect core columns L3 (2 EA) 3264 0
Install L1 secondary steel 1259 0
Install L2 secondary steel 1134 0
Install L3 secondary steel 1301 0
Receiver installation man-hours 12,768 0
9.6 General scope of field work required for receiver panel
assemblies
Receiver panel assemblies
Top adjust assembly
Bolt connection
Lower adjust assembly
Bolt connection
Shim plates
Linkage attachment
Bolt connection
Linkage assembly
Panel
9.7 Receiver panel assembly estimate data
9.7.1 Assemble and erect receiver panels sheet 1
Description MH Unit
Receiver panel assemblies
Top adjust assembly 8 EA
Bolt connection 0.25 EA
Lower adjust assembly 8 EA
Bolt connection 0.25 EA
Shim plates 2 EA
Linkage attachment 4 EA
Bolt connection 0.25 EA
Linkage assembly 10 EA
Panel 80 EA