Page 217 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 217
Solar thermal power plant Chapter 9 193
9.8 Receiver panel assembly installation estimate
9.8.1 Assemble and erect receiver panels sheet 1
Historical Estimate
Description MH Qty Unit Qty Unit IW
Receiver panel assemblies 0
Top adjust assembly 8 14 EA 0 EA 0
Bolt connection 0.25 84 EA 0 EA 0
Lower adjust assembly 8 14 EA 0 EA 0
Bolt connection 0.25 84 EA 0 EA 0
Shim plates 2 14 EA 0 EA 0
Linkage attachment 4 14 EA 0 EA 0
Bolt connection 0.25 56 EA 0 EA 0
Linkage assembly 10 14 EA 0 EA 0
Panel 80 14 EA 0 EA 0
9.9 Receiver panel assembly estimate data
9.9.1 Assemble and erect receiver panels sheet 1
Description MH Unit
Receiver panel assemblies
Top adjust assembly 8 EA
Bolt connection 0.25 EA
Lower adjust assembly 8 EA
Bolt connection 0.25 EA
Shim plates 2 EA
Linkage attachment 4 EA
Bolt connection 0.25 EA
Linkage assembly 10 EA
Panel 80 EA