198 Industrial Process Plant Construction Estimating and Man-Hour Analysis


            9.21 General scope of field work required for each air cooled
            condenser


               Air Cooled Condenser
               Scope of Work-Field Erection
               Off-load and store ACC equipment (transport material to work area)
               Erect structural steel incl. stairs and access platforms
               Erect structural steel modules 1–6
               Fan duct support steel modules 1–6
               Preassemble stairways at grade and set and secure
               Preassemble external walkways at grade and set and bolt up
               Upper structure A-frame steelwork
               Field assemble fan deck incl. fans, gearbox’s and fan cowls
               Fan inlet cowl and fan screens
               Motor support bridge
               Erect and install wind wall
               Erect and weld tube bundles
               Erect and weld condensate headers
               Field assemble street steam duct
               Erect and weld interconnecting street pipe
               Erect weld interconnecting equipment pipe
               Field assemble transition duct to steam turbine
               Field assemble street steam duct
               Field assemble risers
               Erect and weld out risers
               Set and assemble shop tanks
               Set and assemble pumps
               Erect and weld out transition to steam turbine
               Set and connect steam jet air ejectors
               Pneumatic testing