Solar thermal power plant Chapter  9 201


             9.22.3 IC equipment & street pipe, wind walls, turbine exhaust duct
             sheet 3


             Description                               MH                Unit
             Erect and weld IC equipment and street pipe
             Handle pipe                               0.050             DI
             Std BW                                    0.50              DI
             Instrument                                2.00              EA
             Valves                                    0.65              DI
             Pipe support                              1.0               DI
             Hydro                                     0.11              LF
             Erection and sheeting of wind walls
             Place sheeting                            0.23              SF
             Fix sheeting with flashing and caulk      0.05              SF
             Tack or screw sheeting                    1.00              EA
             Erect and weld turbine exhaust duct
                    00
             Handle 48 diameter duct                   10.00             EA
                       00
             Weld duct; 48 diameter   .75 WT BW        1.15              LF
                                  00
             48 Diameter manhole                       1.7               DI
               00
             Weld in nozzle with reinforcement pad     2.25              LF
             Install and align embedded plates         8.0               EA
             Weld together saddles and weld stiffeners  4.0              EA
             Install saddles                           4.0               EA
             Bolt saddles to foundation                2.0               EA
             Place duct sections                       10.0              EA
             Grout support saddles                     8.0               EA
             Weld vanes into elbow
             Install partition plate                   80.0              EA
             Weld partition plate .86 BW               1.15              LF
                             00
             Install vanes                             4                 EA
             Weld vanes fillet weld                    2                 EA
             Cut lifting lug                           2                 EA
             Instrumentation                           4                 EA
             Remove blank plate                        0.15              EA
             Install stiffener plate                   0.6               EA
             10 s80 BW                                 7.5               EA
               00
             10 s80 fillet weld                        7.5               EA
               00
   220   221   222   223   224   225   226   227   228   229   230