202 Industrial Process Plant Construction Estimating and Man-Hour Analysis


            9.22.4 Street steam duct sheet 4

            Description                                 MH              Unit
            Field assemble street steam duct
            Handle 20 –6 diameter duct                  10.00           EA
                      00
                    0
            Handle drain pot                            10.00           EA
            Erect platform                              10.00           EA
            Field weld with slip ring .75 BW            1.15            LF
                                00
            Weld duct; 20 –6 diameter   .75 WT BW       1.15            LF
                      0
                                    00
                         00
            Fit up and Weld .75 BW                      1.15            LF
                          00
            Install and align embedded plates           8.00            EA
            Weld together saddles and weld stiffeners   4.00            EA
            Install saddles                             4.00            EA
            Bolt saddles to foundation                  2.00            EA
            Place duct sections                         10.00           EA
            TED-XX handle duct                          10.00           EA
            Grout support saddles                       8.00            EA
            Reinforcement pad                           1.15            LF
            9.22.5 Erect & weld turbine exhaust duct risers sheet 5

            Description                                 MH              Unit
            Erection and welding of turbine exhaust duct risers
            Erect duct section, duct with elbow         10.00           EA
            Handle duct section, duct section with elbow  10.00         EA
            Fit up and weld .75 BW
                          00
            FFW                                         1.15            LF
            FW                                          1.15            LF
            Install and align embedded plates           8.00            EA
            Weld together saddles and weld stiffeners   4.00            EA
            Install saddles                             4.00            EA
            Bolt saddles to foundation                  2.00            EA