Solar thermal power plant Chapter  9 205



                                     Historical         Estimate
             Description        MH     Qty    Unit  Qty  Unit  BM   IW   MW
             Pipe hanger with   10.00  2.00   EA    0.00  EA        0
               turnbuckle and clevis
             Install steam saddles  10.00  3.00  EA  0.00  EA       0
             Bolt connection    0.15   74.00  EA    0.00  EA        0
             Fan inlet cowl and fan                            0    0    0
               screens
             Fan screen supports  2.00  12.00  EA   0.00  EA        0
             Fan screen modules  3.00  5.00   EA    0.00  EA        0
             Mount fan cowl segments  2.00  12.00  EA  0.00  EA     0
               and top ring
             Bolt connection    0.15   36.00  EA    0.00  EA        0
             Install fan deck plates  2.00  12.00  EA  0.00  EA     0