Solar thermal power plant Chapter 9 205
Historical Estimate
Description MH Qty Unit Qty Unit BM IW MW
Pipe hanger with 10.00 2.00 EA 0.00 EA 0
turnbuckle and clevis
Install steam saddles 10.00 3.00 EA 0.00 EA 0
Bolt connection 0.15 74.00 EA 0.00 EA 0
Fan inlet cowl and fan 0 0 0
screens
Fan screen supports 2.00 12.00 EA 0.00 EA 0
Fan screen modules 3.00 5.00 EA 0.00 EA 0
Mount fan cowl segments 2.00 12.00 EA 0.00 EA 0
and top ring
Bolt connection 0.15 36.00 EA 0.00 EA 0
Install fan deck plates 2.00 12.00 EA 0.00 EA 0