Page 227 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 227

Solar thermal power plant Chapter  9 203


             9.22.6 Risers, shop tanks sheet 6

             Description                         MH                      Unit
             Field assemble risers
             Handle duct                         10.0                    EA
             Expansion joint 8 –6 00             10.0                    EA
                         0
             Set and assemble shop tanks
             Set condensate tank                 40.0                    EA
             Set deaerator tank
             3 –11 diameter                      20.0                    EA
              0
                 00
             8 –6 diameter                       20.0                    EA
              0
                00
             Fit up and weld
             .5 x25                              0.75                    LF
              00
             .5 x54                              0.75                    LF
              00
             Perforated plate                    20.0                    EA
             Wire mesh                           20.0                    EA
             9.22.7 Pumps, expansion joint, test sheet


             Description                                       MH        Unit
             Pumps
             Set pump skid and pumps                           120.0     EA
             Erection and welding of expansion joint (dog bone) at turbine connection
             Weld together upper dog bone holder (including internal braces)
             Handle holder plates                              4.0       EA
             Handle corner section                             4.0       EA
             Fit up and weld holder plates 1.8 thick           4.0       EA
                                    00
             Fit up and weld corner plates 1.1/16 thick and 7/8 thick  4.2  LF
                                                00
                                      00
             Internal braces 5 diameter std pipe               4.0       EA
                        00
             Fillet weld                                       2.0       EA
             Set upper dog bone to steam-turbine duct          40.0      EA
             Fit up and weld to SPX connection 3/4 thick       1.1       LF
                                       00
             Fit up and weld SPX to turbine exhaust duct 2 1/4 thick  2.5  LF
                                               00
             Install dog bone templates                        2.0       EA
             Rod bar                                           2.0       EA
             Remove steel dog bone templates                   2.0       EA
             Install rubber and dog bone                       1.0       EA
             Clamping piece splice                             1.0       EA
             Field erection bolts                              0.2       EA
             Pneumatic testing
             Pneumatic testing                                 1200      TEST