204 Industrial Process Plant Construction Estimating and Man-Hour Analysis


            9.23 Air cooled condenser installation estimate
            9.23.1 Structural steel module/fan duct, stairways & walkways,
            A-frame & fan cowl/screens sheet 1

                                     Historical        Estimate
            Description         MH    Qty     Unit  Qty  Unit  BM   IW  MW

            Erect module structural                            0    0   0
              steel
            Erect and temporarily  2.50  11.26  TON  0.00  TON      0
              bolt structural steel
            Bolt connection     0.15  84.00   EA   0.00  EA         0
            Moment weld         4.00  8.00    EA   0.00  EA         0
            Handle and place    5.00  24.00   EA   0.00  EA         0
              transverse
            Baseplate           2.00  10.00   EA   0.00  EA         0
            Grout baseplate     1.40  36.00   SF   0.00  SF         0
            Fan duct support steel                             0    0   0
              module
            Erect and temporarily  2.50  1.50  TON  0.00  TON       0
              bolt structural steel
            Bolt connection     0.15  1.33    EA   0.00  EA         0
            Preassemble stairways at                           0    0   0
              grade and set
            Unload, assemble, and  0.10  19.94  SF  0.00  SF        0
              install frame
            Install handrail    0.20  8.39    LF   0.00  LF         0
            Install stairs      0.85  3.78    LF   0.00  LF         0
            Install grading     0.17  15.67   SF   0.00  SF         0
            Erect and temporarily  2.50  0.42  TON  0.00  TON       0
              bolt structural steel
            Grout baseplate     1.40  0.22    SF   0.00  SF         0
            Bolt connection     0.15  2.53    EA   0.00  EA         0
            Baseplate           2.00  0.06    EA   0.00  EA         0
            Preassemble walkways                               0    0   0
              at grade and set
            Preassemble walkways,  0.20  94.37  SF  0.00  SF        0
              set, and Bolt
            Upper structure A-frame                            0    0   0
              steelwork
            Erect and temporarily  2.50  8.52  TON  0.00  TON       0
              bolt structural steel
            Seal plate          2.00  20.00   EA   0.00  EA         0
            Access door frame   10.00  1.00   EA   0.00  EA         0
            Cut sheeting to size  0.002  626.00  SF  0.00  SF       0
            Place sheeting      0.23  420.00  SF   0.00  SF         0
            Fix sheeting with flashing  0.05  626.00  SF  0.00  SF  0
              and caulk
            Tack or screw sheeting  1.00  25.00  EA  0.00  EA       0
            Install access door  10.00  1.00  EA   0.00  EA         0
                                                                    Continued