194 Industrial Process Plant Construction Estimating and Man-Hour Analysis
9.10 Receiver panel assembly installation estimate
9.10.1 Assemble and erect receiver panels sheet 1
Historical Estimate
Description MH Qty Unit Qty Unit IW
Receiver panel assemblies 0
Top adjust assembly 8 14 EA 0 EA 0
Bolt connection 0.25 84 EA 0 EA 0
Lower adjust assembly 8 14 EA 0 EA 0
Bolt connection 0.25 84 EA 0 EA 0
Shim plates 2 14 EA 0 EA 0
Linkage attachment 4 14 EA 0 EA 0
Bolt connection 0.25 56 EA 0 EA 0
Linkage assembly 10 14 EA 0 EA 0
Panel 80 14 EA 0 EA 0
9.11 General scope of field work required for thermal enclosure
Thermal enclosure
External frame assemblies
Back blanket assemblies
Side blanket
Gap blanket
Vert spring hanger boots
Spring hanger
Boot header pipe
Bolt connection
9.12 Receiver thermal enclosure estimate data
9.12.1 Assemble and erect thermal enclosure sheet 1
Description MH Unit
Thermal enclosure
External frame assemblies 17.2 EA
Back blanket assemblies 4.0 EA
Side blanket 4.0 EA
Gap blanket 4.0 EA
Vert spring hanger boots 2.0 EA
Spring hanger 2.0 EA
Boot header pipe 4.0 EA
Bolt connection 0.1 EA