184   Industrial process plant construction estimating and man-hour analysis


            8.40 Structural steel and boiler casing estimate data
            8.40.1 Structural steel and boiler casing sheet 1


            Description                                       MH        Unit
            Erect boiler structural steel (stairs, platforms, grating, and handrails)
            Main steel                                        24.00     Ton
            Platform framing                                  0.15      SF
            Grating                                           0.20      SF
            Handrail                                          0.25      LF
            Erect penthouse steel                             24.00     Ton
            Install platform, grating, and handrail at El. 100 -0 to 184 0
                                               00
                                                     0 00
                                              0
            Platform framing                                  0.15      SF
            Grating                                           0.20      SF
            Handrail                                          0.25      LF
            Install stair nos. 1 and 2
            Structural steel                                  24.00     Ton
            Platform framing                                  0.15      SF
            Grating                                           0.20      SF
            Handrail                                          0.25      LF
            Stair treads                                      0.85      EA
            Flues and ducts—with supports, expansion joints, and dampers  40.00  Ton
            Coupling guards                                   14.00     Ton
            Erect casing—generating bank, boiler, and penthouse  62.00  Ton