184 Industrial process plant construction estimating and man-hour analysis
8.40 Structural steel and boiler casing estimate data
8.40.1 Structural steel and boiler casing sheet 1
Description MH Unit
Erect boiler structural steel (stairs, platforms, grating, and handrails)
Main steel 24.00 Ton
Platform framing 0.15 SF
Grating 0.20 SF
Handrail 0.25 LF
Erect penthouse steel 24.00 Ton
Install platform, grating, and handrail at El. 100 -0 to 184 0
00
0 00
0
Platform framing 0.15 SF
Grating 0.20 SF
Handrail 0.25 LF
Install stair nos. 1 and 2
Structural steel 24.00 Ton
Platform framing 0.15 SF
Grating 0.20 SF
Handrail 0.25 LF
Stair treads 0.85 EA
Flues and ducts—with supports, expansion joints, and dampers 40.00 Ton
Coupling guards 14.00 Ton
Erect casing—generating bank, boiler, and penthouse 62.00 Ton