Page 198 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 198

174   Industrial process plant construction estimating and man-hour analysis


            8.36.5 Set plates, rapper rods, Mfg. plates, penthouse, diffuser,
            alignment, rectifiers sheet 5


            Description                                       MH        Unit
            Set precipitator perforated plates
              Set perforated plate sections                   10.00     Ea.
              Weld perforated plate sections                  0.35      LF
              Place and weld clips                            1.50      Ea.
            Set rapper rods
            Rapper sleeves, shafts and insulators, DE alumina rapper shafts  1.10  Ea.
              Seal weld sleeves                               0.35      Ea.
            Set support bushings/mfg. plates
            Set and weld, bolt mfg. plates                    1.00      Ea.
              Set support bushings                            0.24      Ea.
            Erect penthouse
              Place and fit penthouse roof sections, sides, and ends  2.5  Ton
              Weld penthouse roof, sides, ends, and corners   2.15      LF
            Erect and weld in/out diffusers                   1.00      Ea.
            Final alignment                                   2.10      Ton
            Set transformer rectifier sets
              Load, haul, offload transformer rectifiers      4.00      Ea.
              Set transformer rectifiers                      20.00     Ea.
              Install rappers                                 3.00      Ea.
              Install rapper controllers                      20.00     Ea.