Coal-fired power plant Chapter  8 161


             8.21 Selective catalytic reduction unit equipment installation
             estimate

             8.21.1 Install selective catalytic reduction unit sheet 1

                                                   Installation man-hour
                                              Historical        Estimate

                                           MH     Unit     Qty   Unit    BM
             Install selective catalytic reduction unit                  0
             SCR reactor                   20.00  Ton            Ton     0
             Assemble shell                20.00  Ton            Ton     0
             Field joint                   0.40   LF             LF      0
             Ammonia grid module           20.00  Ton            Ton     0
             Field joint                   0.40   LF             LF      0
             Remove shipping angles        40.00  Module         Module  0
             Install tie plate             40.00  Module         Module  0
             Seal frame                    20.00  Ton            Ton     0
             Catalyst modules              10.00  EA             Ton     0
             Install catalyst              4.00   EA             EA      0




             8.22 Selective Catalytic Reduction Unit Installation Man Hours


                                                          Estimated    Actual
                                                          BM           BM
             Install selective catalytic reduction unit   0            0
             Selective catalytic reduction unit installation man-hours  0  0