Coal-fired power plant Chapter 8 161
8.21 Selective catalytic reduction unit equipment installation
estimate
8.21.1 Install selective catalytic reduction unit sheet 1
Installation man-hour
Historical Estimate
MH Unit Qty Unit BM
Install selective catalytic reduction unit 0
SCR reactor 20.00 Ton Ton 0
Assemble shell 20.00 Ton Ton 0
Field joint 0.40 LF LF 0
Ammonia grid module 20.00 Ton Ton 0
Field joint 0.40 LF LF 0
Remove shipping angles 40.00 Module Module 0
Install tie plate 40.00 Module Module 0
Seal frame 20.00 Ton Ton 0
Catalyst modules 10.00 EA Ton 0
Install catalyst 4.00 EA EA 0
8.22 Selective Catalytic Reduction Unit Installation Man Hours
Estimated Actual
BM BM
Install selective catalytic reduction unit 0 0
Selective catalytic reduction unit installation man-hours 0 0