160   Industrial process plant construction estimating and man-hour analysis


            8.18 Air heater installation man hours

                                                 Estimated   Actual
                                                 BM          BM

                      Tube sheets                0           0
                      Air heater installation man-hours  0   0




            8.19 General scope of field work required for each selective
            catalytic reduction unit
               SCR reactor
               Assemble shell
               Field joint
               Ammonia grid module
               Field joint
               Remove shipping angles
               Install tie plate
               Seal frame
               Catalyst modules
               Install catalyst



            8.20 Selective catalytic reduction unit estimate data

            8.20.1 Install selective catalytic reduction unit sheet 1

                      Description                 MH         Unit
                      Assemble shell; set SCR reactor  20.00  Ton
                      Field joint                 0.40       LF
                      Ammonia grid module         20.00      Ton
                      Remove shipping angles      40.00      Module
                      Install tie plate           40.00      Module
                      Seal frame                  20.00      Ton
                      Catalyst modules            10.00      EA
                      Install catalyst            4.00       EA