Page 247 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 247

Sample estimates Chapter  11 225


             11.4 Sample estimate for assembly receiver tower IC pipe

             Process piping estimate form

             Facility:
             Work scope:
                            Pipe                      Unit              Total

             Description    Size     Unit    Qty      MH      Factor    MH














             Column totals



             11.4.1 Handle and install pipe -welded joint sheet 1

             Facility: solar plant
             Work scope: handle and install
             pipe—welded joint
                                         Pipe                           Total

             Description                 Size  Unit  Qty  MH/LF  Factor  MH
             Assembly receiver tower IC pipe
             Cold supply sch 20S SA-312 TP 347H  16  LF  32  1.12  1.00  36
             Jumper sch 20S SA-312 TP 347H  16  LF  97    1.12   1.00   109
             Crossover sch 20S SA-312 TP 347H  16  LF  83  1.12  1.00   93
             Discharge sch 20S SA-312 TP 347H  16  LF  23  1.12  1.00   26
             Downcomer sch 20S SA-312 TP 347H  20  LF  88  1.40  1.00   123
             Drain sch 10S SA-312 TP 347H  6   LF   48    0.42   1.00   20
             Drain header sch 10S SA-312 TP 347H  10  LF  90  0.70  1.00  63
             Drain header sch 10S SA-312 TP 347H  6  LF  5  0.42  1.00  2
             Receiver vent sch 10S SA-312 TP  10  LF  136  0.70  1.00   95
               347H
             Circuit 2 vent sch 10S SA-312 TP 347H  4  LF  139  0.28  1.00  39
             ECV vent sch 10S SA-312 TP 347H  8  LF  27   0.56   1.00   15
             Column totals                          736                 585