226 Industrial Process Plant Construction Estimating and Man-Hour Analysis


            11.4.2 Welding BW, SW, & PWHT—arc uphill sheet 2

            Facility: solar plant
            Work scope: welding BW, SW,
            PWHT—arc uphill
                                         Pipe                           Total

            Description                  Size  Unit  Qty  MH/JT  Factor  MH
            Cold supply sch 20S SA-312 TP 347H  16  EA  4  9.6   2.23   86
            Jumper sch 20S SA-312 TP 347H  16  EA   33   9.6     2.23   706
            Crossover sch 20S SA-312 TP 347H  16  EA  12  9.6    2.23   257
            Discharge sch 20S SA-312 TP 347H  16  EA  4  9.6     2.23   86
            Downcomer sch 20S SA-312 TP 347H  20  EA  6  12      2.45   176
            Drain sch 10S SA-312 TP 347H  6    EA   24   3.6     1.65   143
            Drain header sch 10S SA-312 TP 347H  10  EA  9  6    1.85   100
            Drain header sch 10S SA-312 TP 347H  6  EA  5  3.6   1.65   30
            Receiver assembly vent sch 10S  10  EA  6    6       1.85   67
              SA-312 TP 347H
            Circuit 2 vent sch 10S SA-312 TP 347H  4  EA  25  2.4  1.61  97
            ECV vent sch 10S SA-312 TP 347H  8  EA  6    4.8     1.74   50
            Column totals                           134                 1796