222 Industrial Process Plant Construction Estimating and Man-Hour Analysis


            11.2 Industrial process plant construction estimating process
            Process plant labor estimating is a process that includes the four steps:

            (1) The first step starts with the quantity takeoff, field-specific scope.
            (2) Step two converts the field-specific scope to quantities using the compar-
                ison method; takeoff represents the complete scope of work.
            (3) The third step is the application of man-hour units to the quantified scope of
                work. The man-hour data tables have been developed from historical data,
                collected from field cost reports, and verified using graphic and regression
                analysis.
            (4) Final step is to enter the unit man-hour rates from the tables and the quan-
                tities from the “takeoff” into the estimate sheet and calculate the direct craft
                man-hours using the unit quantity method (man-hour rate   “takeoff” quan-
                tities). The estimate man-hours are compared with the historical man-hours.

            11.3 Sample estimate construction estimating process

            Table 11.3.1 Example field erection fan inlet cowl and fan screens
            (1) The first step starts with the quantity takeoff, field-specific scope.
                Fan inlet cowl and fan screens
                Fan screen supports
                Fan screen modules
                Mount fan cowl segments and top ring
                Bolt connection
                Install fan deck plates
            (2) Convert the field-specific scope to quantities using the comparison method.
            (3) The third step is the application of man-hour units to the quantified scope of
                work. The man-hour data tables have been developed from historical data,
                collected from field cost reports, and verified using graphic analysis.


              TABLE 11.3.1 MHₔ 5 estimate for increased fan inlet cowl and fan screens
              quantities
              Estimate—ACC-solar power plant-fan inlet  Historical  Estimate
              cowl screen
              Description                         Qty    Unit  Qty     Unit
              Fan inlet cowl and fan screens
              Fan screen supports                 12.00  EA    15.00   EA
              Fan screen modules                  5.00   EA    6.25    EA
              Mount fan cowl segments and top ring  12.00  EA  15.00   EA
              Bolt connection                     36.00  EA    45.00   EA
              Install fan deck plates             12.00  EA    15.00   EA