Solar thermal power plant Chapter 9 215
9.25 Solar plant equipment man hour breakdown
Actual Estimate
Facility—solar plant equipment MH BM PF IW MH
Receiver installation man-hours 12,768 0 0
Receiver panel assemblies installation man-hours 9226 0 0
Air cooled condenser (10 cell)—installation man-hours 24,890 0 0 0 0
Solar plant project man-hours 46,884 0 0 0 0