Solar thermal power plant Chapter  9 215


             9.25 Solar plant equipment man hour breakdown

                                                    Actual      Estimate
             Facility—solar plant equipment         MH     BM   PF  IW   MH

             Receiver installation man-hours        12,768          0    0
             Receiver panel assemblies installation man-hours  9226  0   0
             Air cooled condenser (10 cell)—installation man-hours  24,890  0  0  0  0
             Solar plant project man-hours          46,884  0   0   0    0