Page 237 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 237
Solar thermal power plant Chapter 9 213
9.23.7 Pumps, expansion joint, test sheet 7
Historical Estimate
Description MH Qty Unit Qty Unit BM IW MW
Pumps 0 0 0
Set pump skid and pumps 120.0 1.00 EA 0.00 EA 0
Install expansion joint at 0 0 0
turbine
Weld together upper dog
bone holder
Handle holder plates 4.0 0.56 EA 0.00 EA 0
Handle corner section 4.0 0.22 EA 0.00 EA 0
Fit up and weld holder 4.0 0.61 EA 0.00 EA 0
plates 1.8 thick
00
Weld corner plates 1.1/16 00 4.2 0.49 LF 0.00 LF 0
thick and 7/8 thick
00
Internal braces 5 diameter 4.0 0.61 EA 0.00 EA 0
00
std pipe
Fillet weld 2.0 1.33 EA 0.00 EA 0
Set upper dog bone to 40.0 0.06 EA 0.00 EA 0
steam-turbine duct
Fit up and weld to SPX 1.1 4.77 LF 0.00 LF 0
connection 3/4 thick
00
Weld SPX to turbine 2.5 4.77 LF 0.00 LF 0
exhaust duct 2 1/4 thick
00
Install dog bone templates 2.0 0.22 EA 0.00 EA 0
Rod bar 2.0 0.44 EA 0.00 EA 0
Remove steel dog bone 2.0 0.22 EA 0.00 EA 0
templates
Install rubber at dog bone 1.0 4.77 EA 0.00 EA 0
Clamping piece splice 1.0 2.96 EA 0.00 EA 0
Field erection bolts 0.2 11.56 EA 0.00 EA 0
Pneumatic testing 0 0 0
Pneumatic testing 1200 0.03 TEST 0.00 TEST 0