Page 57 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 57

28  Industrial Process Plant Construction Estimating and Man-Hour Analysis


            2.3.3 Welding—SOL, TOL, and WOL
            Facility—Oil refinery

            Man-hours per SOL, TOL, and WOL
                                      Wall thickness in inches
              Pipe
              size  Up to 0.375 00  0.406 –0.500 00  0.562 –0.688 00  0.718 –0.938 00  1.031 –1.219 00
                                  00
                                                         00
                                              00
                                                                     00
              0.5      2.00       2.30       3.80        4.50        5.20
              0.75     2.00       2.30       3.80        4.50        5.20
               1       2.00       2.30       3.80        4.50        5.20
              1.5      2.00       2.30       3.80        4.50        5.20
               2       2.00       2.30       3.80        4.50        5.20
              2.5      2.25       2.50       4.75        5.50        6.75
               3       2.70       3.00       5.70        6.60        8.10
               4       3.60       4.00       7.60        8.80       10.80
               6       5.40       6.00       11.40       13.20      16.20
               8       7.20       8.00       15.20       17.60      21.60
               10      9.00      10.00       19.00       22.00      27.00
               12     10.80      12.00       22.80       26.40      32.40
               14     12.60      14.00       26.60       30.80      37.80
               16     14.40      16.00       30.40       35.20      43.20
               18     16.20      18.00       34.20       39.60      48.60
               20     18.00      20.00       38.00       44.00      54.00
               24     21.60      24.00       45.60       52.80      64.80
            SOL, TOL, and WOL welds; two times BW (includes cut, prep, and fit up).
            Wall thickness of the pipe used for weld determines man-hours that will apply.
            Apply percentages for welding alloys and nonferrous welds.
   52   53   54   55   56   57   58   59   60   61   62