Process piping Chapter  2 29


             2.3.4  PWHT craft support labor
             Facility—Oil refinery

                           Man-hour per joint
                            Pipe size                     MH

                              0.5                        1.00
                              0.75                       1.00
                               1                         1.00
                              1.5                        1.00
                               2                         1.00
                              2.5                        1.13
                               3                         1.35
                               4                         1.80
                               6                         2.70
                               8                         3.60
                              10                         4.50
                              12                         5.40
                              14                         6.30
                              16                         7.20
                              18                         8.10
                              20                         9.00
                              24                         10.80
                           Place and remove insulation from weld joint.