30  Industrial Process Plant Construction Estimating and Man-Hour Analysis


            2.3.5 Field bolt up of flanged joints by weight class
            Facility—Oil refinery

                 Man-hours per joint
                                             Pressure rating

                 Pipe size     150#/300#      600#/900#      1500#/2500#
                    0.5           1.00           1.20           1.60
                   0.75           1.00           1.20           1.60
                    1             1.00           1.20           1.60
                    1.5           1.00           1.20           1.60
                    2             1.00           1.20           1.60
                    2.5           1.00           1.25           1.63
                    3             1.20           1.50           1.95
                    4             1.60           2.00           2.60
                    6             2.40           3.00           3.90
                    8             3.20           4.00           5.20
                    10            4.00           5.00           6.50
                    12            4.80           6.00           7.80
                    14            5.60           7.00           9.10
                    16            6.40           8.00           10.40
                    18            7.20           9.00           11.70
                    20            8.00          10.00           13.00
                    24            9.60          12.00           15.60
                 Man-hours per joint to bolt-up valves, expansion joints, flanged fittings, and spools.