24  Industrial Process Plant Construction Estimating and Man-Hour Analysis


            2.2.1 General welding notes
            Manual butt welds—wall thickness of the pipe determines man-hours that will
            apply per joint.
                                                                          00
               Postweld heat treatment (PWHT) butt welds greater than or equal to 0.750 .
               PWHT craft support—man-hours for craft to warp/and remove pipe insula-
               tion for stress relief.
               Apply percentages for welding alloys and nonferrous butt welds.
               Preheating and stress relieving butt welds are not included.
            Olet welds—man-hours are two times butt weld and include cutting, placing,
            and welding per connection.
               Stub in weld—man-hours are 1.5 times butt weld and include cutting, plac-
            ing, and welding per connection.
               Socket welds—man-hours include fit up and welding per joint.
               Hydrotest pipe—man-hours to place/remove blinds, open/close valves,
            removal/replacement of valves and specialty items and pipe sections as required
            and drain lines after testing.