36  Industrial Process Plant Construction Estimating and Man-Hour Analysis


            2.4.4 PWHT craft support labor
            Facility—Diesel power plant

                             Man-hour per joint
                             Pipe size           MH per joint

                               0.5                  1.00
                               0.75                 1.00
                                1                   1.00
                               1.5                  1.00
                                2                   1.00
                               2.5                  1.63
                                3                   1.95
                                4                   2.60
                                6                   3.90
                                8                   5.20
                                10                  6.50
                                12                  7.80
                                14                  9.10
                                16                  10.40
                                18                  11.70
                                20                  13.00
                                24                  15.60
                             Insulate and remove insulation from weld joint.