Process piping Chapter  2 37


             2.4.5  Field bolt up of flanged joints by weight class
             Facility—Diesel power plant

                  Man-hours per joint
                                              Pressure rating

                  Pipe size     150#/300#      600#/900#      1500#/2500#
                    0.5           0.90           1.20            1.60
                    0.75          0.90           1.20            1.60
                     1            0.90           1.20            1.60
                    1.5           0.90           1.20            1.60
                     2            0.90           1.20            1.60
                    2.5           1.13           1.38            1.63
                     3            1.35           1.65            1.95
                     4            1.80           2.20            2.60
                     6            2.70           3.30            3.90
                     8            3.60           4.40            5.20
                    10            4.50           5.50            6.50
                    12            5.40           6.60            7.80
                    14            6.30           7.70            9.10
                    16            7.20           8.80           10.40
                    18            8.10           9.90           11.70
                    20            9.00           11.00          13.00
                    24            10.80          13.20          15.60
                  Man-hours per joint to bolt-up valves, expansion joints, flanged fittings, and spools.