44  Industrial Process Plant Construction Estimating and Man-Hour Analysis


            2.5.5 PWHT craft support labor
            Facility—Solar power plant

                           Man-hour per joint
                           Pipe size                     MH

                              0.5                        1.00
                             0.75                        1.00
                              1                          1.00
                              1.5                        1.00
                              2                          1.00
                              2.5                        1.13
                              3                          1.35
                              4                          1.80
                              6                          2.70
                              8                          3.60
                              10                         4.50
                              12                         5.40
                              14                         6.30
                              16                         7.20
                              18                         8.10
                              20                         9.00
                              24                         10.80
                           Place and remove insulation from weld joint.